The footings were stripped on March 19, the same day the wall forms were delivered. Late Monday afternoon March 23 all the outside wall forms were in place ready for the structural reinforcing bar. We set the elevation of the home so the front left corner of the house has less about 6" of slope from the house to the sidewalk. The garage floor will be dropped by 3' to accommodate the slope in the sidewalk, this will give the left side of the driveway 4" of slope from the front of the garage to the sidewalk while the right side of the driveway will follow natural slope of the sidewalk.