Thursday, March 19, 2015

Excavation & Footings

Excavation started early march, we added fill material from the folks at Kirshner Mountain Developments placed it with our excavator and packed in 12" lifts with a 66" drive on roller packer.  Geotechnical inspection were inspected and passed by  Horizon Geotechnical.  The lot was surveyed by BC Surveyors and we placed the forms exactly on top of the survey pins.  The footing forms and placement of the 15 mm steel rebar was inspected by AccuTtruss, our structural engineer and the city of Kelowna.  The footings were poured the same day the building permit was issued, on March 18.